4News -> Industry dynamic

Oil seal needs to pay attention to


1. Preparations and precautions before starting

a, comprehensively check the mechanical seal, and whether the attachments and pipelines are installed properly and meet the technical requirements.

b. Perform a static pressure test before starting the mechanical seal to check for leaks in the mechanical seal. If there are more leaks, you should find out the reasons and try to eliminate them. If it is still invalid, it should be disassembled and reinstalled. Generally, the static pressure test pressure is 2~3 kg/cm2.

c. Press the pump to turn the disc to check if it is light and even. If the car is struggling or not moving, check whether the assembly size is wrong and the installation is reasonable.

2, installation and outage

a. Keep the sealed chamber filled with liquid before starting. For transporting a solidified medium, steam is applied to heat the sealed chamber to melt the medium. The car must be driven before starting to prevent the soft ring from breaking due to sudden start.

b. For mechanical seals using the pump external seal system, the oil seal system should be activated first. Finally stop the oil sealing system after parking.

c. After the hot oil pump is stopped, the cooling water of the oil sealing chamber and the end face seal cannot be stopped immediately. When the oil temperature of the end seal is lowered to below 80 degrees, the cooling water can be stopped to avoid damage to the sealing parts.

3, running

a, if there is a slight leak after the pump starts, it should be observed for a while. If the leakage is still not reduced if the operation is continued for 4 hours, the pump should be stopped.

b, the operating pressure of the pump should be stable and the pressure fluctuation should be no more than 1 kg/cm 2 .

c. When the pump is in operation, evacuation should be avoided to avoid dry friction and seal damage on the sealing surface.

d, the sealing situation should be checked frequently. During operation, when the leakage exceeds the standard, the heavy oil is not more than 5 drops/min, and the light oil is not more than 10/min. If there is no improvement trend within 2-3 days, the pump should be stopped to check the sealing device.

Each customer has a quality file, which is tracked regularly. The customer feedback problem, the fastest 1 hour to give the customer satisfaction solution.